Meeting Summary - 12/03/24 Joint Legislative Oversight Committee On Grid Reliability

1 – Call to Order
2 – Roll Call
3 – Organizational Business
- Adoption of committee rules for the joint Senate and House Grid Reliability Legislative Oversight Committee.
- Chair Hunter moved to adopt the committee rules with no objections.
- Creation of the Grid Reliability Legislative Oversight Committee by House Bill 1500 to review legislation related to electricity market regulation by the 87th and 88th legislatures.
- Significance of collaboration between House and Senate to maintain and enhance the electric grid’s reliability and resiliency.
- Impact of Senate Bill 3 post-Winter Storm Uri, which strengthened the Texas power grid reliability.
- Last legislative session’s focus on new dispatchable generation and market operation improvements with Senate Bill 2627 and House Bill 1500.
- Prioritization of system hardening and planning with House Bills 2555 and 5066.
- Hurricane Beryl highlighted shortcomings in the electric infrastructure and renewed focus on resiliency.
- Anticipation of insights from industry leaders on recent reforms and future priorities.
- Acknowledgments and appreciations from Chairman Hunter and other members towards each other and their collaborative work.
4 – Invited Testimony – Grid Reliability
Panel 1 Invited Testimony
▶️ – Connie Corona, Executive Director, PUCT, Invited Testimony
- Updates on Texas Energy Fund Loan program, including staff recommendations for replacing 1200 megawatts from a denied project, with accelerated background checks.
- Reliability plan for the Permian Basin approved by commissioners, with analysis on extra high voltage transmission options and stakeholder engagement underway.
- Publication of the Severe Weather Preparedness and Response Investigation Report and two proposed rulemakings: outage tracker maintenance and emergency communications.
- Challenges with mass transfer of customer emergency contact information and options for voluntary enrollment in TDU outage notifications.
- Recommendations for customer communications improvements, including information about service restoration and vegetation hazard reporting.
- Proposal for a framework and penalty structure to assess utility service quality during major outages.
- Legislative recommendations in the upcoming agency biennial report for improving commission efficiencies and infrastructure standards.
- Invitation for legislative input and readiness to answer questions from the commission members.
▶️ – Woody Rickerson, SVP and COO, ERCOT, Invited Testimony
- ERCOT’s forecasting models have been updated to include TSP load forecasts, with a significant increase to 150 gigawatts by 2030 due to House Bill 5066.
- The Regional Transmission Plan considers upgrading from 345-kV to 765-kV due to unprecedented load growth, similar to a historical upgrade in the 1960s.
- The Permian Basin Reliability study also explores transmission upgrades with 345-kV and 765-kV options included in ERCOT’s overall plan, with decisions expected from PUC in May.
- Large load growth is occurring with 63 gigawatts tracked, 6.3 gigawatts approved to energize, and 3.6 gigawatts energized, posing unique challenges for grid stability.
- Battery and solar energy account for 83% of new generation interconnection, with a total of 371 gigawatts in the queue, alongside 26 gigawatts of gas-fired projects.
- ERCOT’s system weatherization and reliability efforts, including 3,000 inspections since winter storm Uri, are recognized as leading initiatives by the NERC winter reliability assessment for 2024.
Panel 1 Q&A
▶️ – Senator Schwertner to Connie Corona, PUC’s Plan for Mobile Generation Misuse
- Discussion on PUC’s investigation of hurricane Beryl and preparedness, focusing on mobile generation misuses.
- Recommendation for utilities to pre-identify site characteristics requiring backup generation.
- Suggestion for utilities to measure needed mobile generation in advance for efficient deployment during storms.
- Inquiry about potential reimbursement plans for ratepayers who paid for unused or misappropriately sized mobile generation.
- Mention of legislation filed for making ratepayers whole and possible redeployment of unused units to San Antonio.
- References to legislation proposed by Senator King and others regarding ratepayer protection.
- Acknowledgment of the need for balancing new wind and solar generation to maintain grid reliability.
▶️ – Senator Schwertner to Woody Rickerson, Impact of Co-Located Generation on Grid Stability
- The growth of large load requires an additional 150 gigawatts by 2030, raising concerns about grid stability.
- Co-located generation and large loads raise policy issues, especially regarding transmission cost allocation.
- Even if load is behind a generator, it still consumes the same amount of power, posing questions about its impact on the grid.
- There is a challenge in outage coordination with co-located large loads since ERCOT loses some control when it becomes a private use network.
- The main issue is transmission cost allocation, socialized across all rate payers, not accounting for loads behind the meter.
- 4CP cost allocation method doesn’t consider behind-the-meter loads, impacting ERCOT’s accounting perspective.
- Transmission system stress has shifted due to solar power, making traditional peak hours obsolete.
- A review of the cost allocation method is needed due to changes in resource mix, with stress occurring more often outside traditional peak hours.
- The Market Analysis Division agrees with recommendations from the independent market monitor to revisit transmission allocation policy in 2025.
- No initial fees are currently imposed on large loads when they plan to add to the grid.
▶️ – Representative Hunter to Connie Corona, Transparency in Utility Bill Charges
- Highlighted public’s concern about undefined charges on utility bills labeled as ‘miscellaneous’, ‘delivery’, and ‘other’.
- Requested Connie Corona and her agency to investigate these charges for transparency before the legislative session.
- Emphasized the need for public awareness about why charges are applied.
- Connie Corona agreed to review and update the committee on utility billing charges & welcomed requests from committee members on specific bills needing investigation.
- Rep. Hernandez Discussed the legislative appropriations request for more resources due to increased caseloads, especially regarding transmission line processing.
- Chairman inquired into penalties for utility service quality during major outages.
- Discussed inclusion of major events in existing penalty measures for service interruptions.
- Senator Zaffirini discussed codifying customer rights to information about service restoration times and emergency contact with providers.
- Explored potential methods for customers to report vegetation hazards, suggesting phone lines and tech-friendly solutions.
▶️ – Senator Zaffirini to Connie Corona, Emergency Communication Plans for Utilities
- Importance of utilities conducting annual emergency drills involving neighboring utilities and local governments.
- Recommendation for pre-emergency communication plans to be required by the legislature or PUC.
- Need for dedicated communication paths and shared plans among partner entities during emergencies.
- Most generation and transmission facilities met the weatherization inspection requirements, with a few exceptions rectified for winter or summer seasons.
- Lessons from international use of 765 equipment include efficient land use and existing U.S. supply chain.
- Efforts to increase public awareness of ERCOT’s website and mobile app through expanded social media presence.
- Lack of prepared metrics to demonstrate improved public usage of the website and app; intention to provide them upon request.
▶️ – Senator Nichols to Woody Rickerson, Power Allocation for Data Centers with Dedicated Generation
- Discussion of the growth in power consumption, driven by data centers.
- Some data centers are contracting for their own power generation.
- Two scenarios for supplying power to data centers: co-located behind the generator or via the grid.
- Behind-the-meter generation is subtracted from grid capacity, not adding load to the grid.
- Generation contracted through the grid keeps the generation apparent in reports but can be misleading about availability.
- Concerns about potential congestion in transmission lines and cost allocation.
- Emphasis on the need for improved separation of resources used off-grid and their impact on grid capacity.
- Data centers’ power draw can be calculated during peak hours using shift factors and 4CP method.
▶️ – Senator Schwertner to Woody Rickerson, TDU Projection Models and Uniformity
- The current methodology for projecting load can be manipulated, prompting discussions on improving this system.
- Issues with 4CP reductions are noted during the critical months from July to September.
- TDUs use different projection models, highlighting concerns about their accuracy and the lack of uniformity.
- A voluntary large load interconnection process is in place for reviewing loads reported by TSPs.
- Duplications of loads within Texas have been detected and removed, but global duplications remain challenging to address.
- No fees are required for foreign loads during interconnection, pending TSPs’ input.
- Concerns exist over the artificial scarcity introduced by current grid management methodologies affecting ancillary services.
- There was an improvement due to process changes in ERCOT’s management for summer 2023 and further updates are planned for next year.
- Discussions on large load connections and their impact on the grid show concerns over cost burden on ratepayers without universal benefits.
- Currently, there is no ability to differentially manage or curtail large loads connected to the grid.
- A voluntary registration program exists only for crypto mines.
▶️ – Representative Hunter to Connie Corona, Simplifying Electric Bill Transparency for Consumers
- Representative Hunter expressed concern about electric bill charges being passed to consumers without clear explanations.
- ERCOT has made efforts to educate consumers by providing resources on social media, but Hunter feels this indicates complexity in understanding bills.
- Hunter suggested many consumers, especially those less technologically savvy, might struggle with accessing online resources for bill explanations.
- The primary concern discussed was the burden of costs and lack of transparency in passing costs to Texans.
- There was a discussion about the absence of a ‘no harm’ certification in Texas to ensure that new projects do not reduce grid megawatts or negatively affect grid function.
- Corona acknowledged the potential benefit of a ‘no harm’ certification policy for Texas and mentioned a possible legislative solution for data centers to switch to backup power during grid scarcity.
- It was clarified that ERCOT and Transmission Service Providers (TSPs) look at projects from a transmission adequacy standpoint, but Texas lacks a generation adequacy or resource adequacy standard.
- The panel transitioned to include speakers from the Office of Public Utility Council and Potomac Economics to discuss related regulatory and economic issues.
Panel 2 Invited Testimony
▶️ – Chris Ekoh, Deputy Public Counsel, OPUC
- Chris Ekoh introduced himself and mentioned the governor’s new public council appointment.
- Clarified a question regarding the cost of ancillary services, mentioning an estimated $12 billion excess cost for ECRS implementation.
- OPUC’s annual public meeting scheduled for December 12th was announced.
- Discussion focused on the rising costs of ancillary services, as dictated by the 87th legislature, with an emphasis on balancing reliability and cost.
- Cost of ancillary services rose by 270% between 2020 and 2022 due to increased conservative procurement post-Winter Storm Uri.
- In 2023, costs increased by 32.4% despite decreases in natural gas and energy prices, attributed to the implementation of ECRS.
- IMM suggested that current ECRS levels could be reduced by 52% and non-spin quantities by 35% without compromising reliability.
▶️ – Jeff McDonald, Director, Potomac Economics
- Jeff McDonald, representing IMM for ERCOT and Potomac Economics, discussed reliability focus in Texas.
- Texas utilizes a market-based approach to reliability, aiming to provide price signals that encourage performance and new investment.
- McDonald has been in his role for nine months and offers a fresh perspective on reliability issues.
- Emphasis on two reliability approaches: enhanced resiliency and development of market reliability products.
- Recent assessments focused on ERCOT’s operational reliability through studies and reports with the PUC.
- Involvement in developing a new product (DORS) to address forecast timing gaps.
- Worked on improving shortage reserve curves for the upcoming real-time co-optimization market framework for next year.
- Goal is to align procurement and pricing of reliability services with their value to Texans.
- Extended focus over the past two years on these market instruments for increased reliability.
- Positive outcomes from the ECRS process, with ERCOT now better positioned to avoid false scarcity conditions.
- Identified potential for reduced procurement of reserves and lower costs for consumers, working with ERCOT to further reduce these procurements.
Panel 2 Q&A
▶️ – Senator Schwertner to Chris Ekoh, Cost Allocation for Non-Residential Load Growth
- Discussion on overprocurement and reserves impacting Texas electricity costs, noting adjustments post-Winter Storm Uri to maintain affordability.
- Focus on non-residential load growth driven by data centers, crypto mining, oil and gas, and new commercial operations.
- Concerns about resource adequacy, interconnection, cost allocation, and cost causation in ERCOT and PUC programs.
- Mention of House Bill 5066 and NPRR1180, related to substantiated load definitions and visibility in load forecasts.
- Emphasis on the need for accurate load forecasting and potential overforecasting risks leading to overinvestment.
- Concerns raised about lack of standardization in methodologies used by TDUs for load forecasting.
- Discussion on possible financial commitments for large loads before grid connection to address phantom load issues.
▶️ – Senator Zaffirini to Chris Ekoh, Strategies to Prevent Load Shedding
- Chris Ekoh discussed the strategy for avoiding load shedding by focusing on avoiding a ‘watch’ trigger, which is a precursor to Energy Emergency Alerts (EEA).
- Current operations aim to prevent grid loading close to 3000 megawatts, at which point EEAs and ancillary services are triggered.
- IMM modeling suggests that reducing the procurement of ancillary services can allow the grid to run effectively.
- Concerns were raised about potential overbuilding of transmission infrastructure if the NPRR 1180 is passed, which could lead to unnecessary costs.
- Overbuilding risk is high due to a provision allowing utility officers to request infrastructure based on forecasted load needs.
- Chris Ekoh emphasized the importance of balancing reliability and affordability of the grid, noting the necessity of evaluating cost implications before implementation.
- He highlighted the high cost of some ERCOT programs, such as ECRS, which was more expensive than initially anticipated.
▶️ – Senator Zaffirini for Jeff McDonald, Understanding 4CP and Its Impact on Utility Bills
- Mr. McDonald provided a high-level overview of 4CP, a technique used in transmission cost allocation.
- 4CP was first applied in 1966 for transmission allocation based on coincident peak load driving the need for new transmission.
- Current transmission investments are driven by factors other than peak load, such as demographic shifts, industrial use, and new resources.
- Costs of transmission are currently allocated broadly across Texas ratepayers, which may not be efficient.
- Exploring a more localized cost allocation to avoid broad distribution of costs across all Texans.
- Discussion on expanding coincident peak measures to 12 times per year or from 15 minutes to one hour.
- Increasing the time from 15 minutes to an hour might reduce inefficiency and difficulty predicting peak periods.
- Acknowledgment that 40% of utility bills are tied to transmission costs, with an expectation for this percentage to grow.
- No specific forecast was provided for the future percentage of transmission costs on utility bills.
Panel 3 Invited Testimony
▶️ – Katie Coleman, TAM, TCC, TxOGA, Invited Testimony
- Representatives for Texas Association of Manufacturers, Texas Chemistry Council, and Texas Oil and Gas Association are concerned about large load issues, fearing negative impacts on industrial development.
- There’s a need to scrutinize numbers related to electric usage and data center development, especially if they don’t align with national expectations.
- Proposals include additional fees for interconnection studies, security requirements, and disclosure of alternative service facilities.
- Stressed the need to differentiate between transmission planning forecast and generation adequacy analysis.
- Emphasized that transmission planning must account for maximum capacity needs, unlike generation adequacy which considers expected peaks with a reserve margin.
- Called for reevaluation of cost allocation methods in transmission investment to ensure they reflect current system needs better than the traditional 4CP method.
- Advocated for consideration of peak demand using a broader definition and for including winter months in analysis.
- Highlighted importance of aligning cost allocation methodology with cost causation.
- Discussed historical colocation practices, emphasizing that industrial support for on-site generation could enhance resource adequacy.
- Expressed readiness to participate in discussions to ensure favorable industrial backed generation development.
▶️ – Julia Harvey, TEC, Invited Testimony
- Julia Harvey represents Texas Electric Cooperatives, which comprises 76 member-owned electric co-ops in Texas.
- Electric Co-Ops are not-for-profit utilities focused on serving member needs, involvement includes retail distribution, wires, transmission, and generation.
- Appreciation was expressed for the PUC efforts on legislative implementation around SB2627 and HB1500.
- The main priority is maintaining affordability and dealing with cost allocation since Co-Ops have no shareholders and are accountable to the people served.
- Concern about cost escalation impacting end users, particularly amidst significant load growth in rural and metropolitan areas.
- Stressed the need for accurate ERCOT load forecasting to support infrastructure development, especially for large loads.
- Emphasis on adjusting transmission cost allocation to prevent disproportionate financial burden on residential end users due to infrastructure serving businesses.
- Acknowledged the obligation to serve large loads despite associated risks, particularly with flexible loads that may avoid transmission costs.
- Highlighted the need to revisit cost allocation under the current consumption-based paradigm.
- Expressed commitment to addressing cost issues and infrastructure build-out collaboratively in the upcoming session.
▶️ – Cathy Webking, TEAM, Invited Testimony
- Kathryn Webking represented TEAM, an industry association of retail electric providers, offering perspectives on serving residential and small commercial customers in Texas.
- Highlighted the benefits of competitive retail service, such as transparency, options, and fixed price contracts for customers.
- Discussed the importance of maintaining the ability for customers to choose the terms of their contracts without speculative pricing for future costs, like the DRRS service.
- Emphasized the need for a one-time adjustment to cover any new costs without burdening current contracts.
- Mentioned the commission’s efforts on legislative implementations, particularly customer communication during emergency events.
- Supported the commission’s approach to making the communication responsibilities of utilities clear to customers, especially during outages.
- Stressed the importance of the public outage tracker and the need for reliable information to help customers make health and safety decisions.
- Mentioned Senate Bill 3’s power alert system and the potential for legislative adjustments to allow broader communication.
- Concluded with appreciation for the opportunity to testify and a willingness to answer questions.
▶️ – Walt Baum, Powering Texans, Invited Testimony
- Walt Baum expressed that the grid is more reliable than at the start of the last session.
- Acknowledged contributions of the legislature, PUC, and ERCOT in improving reliability.
- Mentioned progress on implementing bills passed in 2021 and 2023.
- Highlighted the Texas Energy Fund’s role in supporting new dispatchable generation.
- Praised the PUC’s adoption of a reliability standard following House Bill 1500.
- Emphasized the need for ancillary services tools to meet the new reliability standard.
- Powering Texans member companies are advancing in the Energy Fund’s due diligence phase.
- Concern about the Energy Fund’s potential impact on the competitive market if it continues indefinitely.
- Stressed the need for stability and caution against numerous changes that might slow current developments.
- Recognized the importance of encouraging data center development in Texas.
- Believes data center development can coexist with grid reliability and benefit the local economy.
- Sees energy market signals as aligned with supporting new generation developments due to load growth.
▶️ – Mark Bell, AECT, Invited Testimony
- Mark Bell represents the Association of Electric Companies of Texas (AECT).
- Acknowledgement of efforts by the PU), ERCOT, and stakeholders in implementing legislative measures.
- House Bill 1500 continues the PUC until 2029 and introduces various industry changes, including new transmission requirements and market operation changes.
- Introduction of the Dispatchable Reserve Reliability Service (DRRS) to encourage new and existing thermal plant operations.
- House Bill 2555, the Texas Resiliency Act, enables utilities to plan for grid resiliency investments.
- The first resiliency plan under House Bill 2555 is approved by the PUC.
- House Bill 5066 revises electric growth evaluation and requires a transmission plan for the Permian Basin.
- Senate Bill 2627 establishes the Texas Energy Fund (TEF), with ongoing application reviews by the PUC.
- The TEF includes $1 billion in grants for non-ERCOT utilities and $1.8 million for the Texas Power Promise Program.
- Overall legislative actions aim to enhance grid reliability and resilience.
Panel 3 Q&A
▶️ – Senator Zaffirini to Cathy Webking, Mandating Emergency Plans by Statute or Rule
- Cathy Webking discussed the necessity of communication plans.
- She supports mandating communication plans by statute or rule.
- Believes the Commission should have statutory authority for these plans.
- Would support clarification or codification if needed.
▶️ – Senator Zaffirini to Katie Coleman, Expanding on Net Peak Analysis
- Discussion on the difference between absolute maximum demand and net peak load, with net peak load affected by low renewable output.
- Transmission planning now considers net peak load more than absolute peak demand.
- Congestion-related projects are often geographically constrained, exemplified by Houston’s electricity import needs due to strict emissions restrictions and water constraints.
- Cost allocation in transmission, such as the postage stamp allocation, aims to avoid disadvantaging economically significant areas like Houston.
- New factors, including net peak demand, are driving transmission development beyond just absolute peak demand.
- 4CP methodology’s economic impact is about 5% of the 85 gigawatt system, benefiting companies but not significantly affecting total demand costs.
- 4CP response and transmission cost avoidance are often practiced by various customers, including commercial entities and municipally owned utilities.
- There are reliability benefits from the 4CP regime because it incentivizes demand reduction during scarcity periods.
- Suggestion to consider non-coincident peak basis cost allocation to ensure equitable transmission cost distribution.
▶️ – Senator Zaffirini to Walt Baum, Requiring Data Centers to Provide Their Own Energy
- Mr. Baum mentioned some data centers are providing their own energy.
- Consideration of the state requiring data centers to provide their own energy.
- Flexibility is needed in structuring deals for data centers providing their own energy.
- Concern that over-prescription by the state could drive demand to other states.
- Importance of ERCOT’s visibility into the energy provisions of data centers.
- Discussions are ensuring ERCOT is involved before decisions are made.
- Consideration of large loads like cryptocurrency mining in energy requirement discussions.
- The PUC and ERCOT have been working on defining and managing large flexible loads.
▶️ – Senator Schwertner to Walt Baum, Position on No Harm Certification for Co-Located Generation
- Discussion on the position regarding no harm certification for co-located generation with large load.
- Senator Schwertner asked about any negative effects on overall grid reliability or net loss of dispatchable generation due to co-located generation.
- No firm position was stated; concerns about maintaining Texas’s image as open for business were noted.
- Mention of the importance of establishing standards for new load requirements.
- Acknowledgement that determining these standards falls within the appropriate jurisdiction.
5 – Public Testimony
▶️ – Glenn Lyons Public Testimony
- Glenn Lyons, an ExxonMobil retiree, spoke about challenges faced by the ERCOT committee.
- Lyons noted that ERCOT’s market design assumed all key parameters were known, leading to issues with adapting to new parameters.
- Compared to more flexible markets, the electricity sector’s slow adaptation is problematic, especially with rapid changes such as the rise of data centers.
- Lyons proposed Consumer Regulated Electricity (CRE) as a solution for rapid growth issues, particularly for data centers.
- CRE utilities could operate independently from the regulated grid, offering faster adaptation without adding costs or reliability concerns to existing grids.
- This proposed model would not require Public Utility Commission (PUC) oversight, allowing for quicker implementation.
- Lyons provided a written testimony, a one-page introduction to CRE, and a draft bill concerning this idea.
▶️ – Brent Bennett Public Testimony
- Brent Bennett from the Texas Public Policy Foundation addressed the committee.
- Emphasized the economic future of Texas depends on meeting reliability expectations at the lowest cost.
- Highlighted two critical points from House Bill 1500, Section 23.
- Discussed the PUC report on transmission and backup power costs for dispatchable and non-dispatchable generators.
- Emphasized the importance of cost allocation for ancillary services not currently addressed, as mandated by Senate Bill 3.
- Mentioned market price volatility increases with the addition of wind and solar energy.
- Current research indicates a billion-dollar impact on consumers in 2023 due to wind and solar.
- Discussed market issues caused by the single market clearing price not accounting for wind and solar variability.
- Exacerbation of market problems due to federal subsidies for wind and solar.
- Reliability standards per HB1500, Section 23 point towards solutions, but firming must apply to all generators.
- Concern that applying firming only to new generation won’t address existing 40 gigawatt wind and solar by 2026.
- Studying economically efficient ways to use firming to benefit ratepayers.
▶️ – Ryan Scott Public Testimony
- Ryan Scott represented Consumer Energy Alliance (CEA), established in 2005 for advocating sensible energy policies for families and businesses.
- CEA advocates for affordable, reliable, and environmentally friendly energy policies benefiting Texans.
- They have a network of 400 member companies and 500,000 individuals nationwide.
- Emphasized balance between traditional and renewable energy sources to meet diverse consumer needs.
- Urged the committee to focus on affordability, reliability, and environmental stewardship in energy policy implementation.
- Critiqued the grid’s reliability post-Winter Storm Uri and other natural disasters, highlighting its impact on the Texas economy.
- Discussed the need for resilient and reliable infrastructure investment for the future.
- Utilities are working on improving resilience without increasing consumer burden.
- Acknowledged the committee’s hard work in overseeing efforts to harden the grid and reduce outages.
▶️ – Larry Lindenschmidt Public Testimony
- Larry Lindenschmidt introduced himself as the Executive Director of the Hill Country Institute and a volunteer with the Citizens Climate Lobby.
- He emphasized the importance of considering extreme weather events, based on a report by the Texas State Climatologist, for grid reliability in Texas.
- Thomas Patock from Texas State University provided insights into climate change and its human-driven impacts on weather events.
- Highlighted risks include drought, wildfires, tornadoes, derechos, floods, hurricanes, and associated damages.
- Stressed the importance of integrating climate science into grid planning to prevent costly long-term infrastructure rebuilding.
- Advocated for funding $2 million to the Public Utility Commission of Texas (PUCT) for a climate action plan.
- Recommended building more transmission lines and ensuring they are built to withstand extreme weather specific to their locations.
- Public testimony was closed after Mr. Lindenschmidt’s presentation, and members expressed appreciation for the discussion.
- The meeting underscored the need for diligent planning ahead of the upcoming legislative session.
6 – Recess
- The Grid Reliability Legislative Oversight Committee has initiated a recess.
- The meeting will resume when called by the chairs.