Articles
November 21, 2024
Meeting Summary - 09/06/24 LFLTF Meeting
1 – Antitrust Admonition – Bill Blevins
2 – Large Load Queue Update – ERCOT Staff
- Julie Stittman, supervisor of the large load integration team, presented the large load interconnection status update.
- Over the past twelve months, the combination of new standalone and co-located projects, as well as several project cancellations, has increased the total queue capacity by 4439 MW.
- Current Large Load Interconnection Queue broken into 4 categories
- Approved to energize
- Planning studies approved
- Under ERCOT review
- No studies submitted
- Approved to energize:1570 MW approved over the past year; total of 5496 MW currently approved, with 2854 MW in load zone west and 2642 MW in other zones.
- The breakdown of approved projects: 4421 MW standalone and 1075 MW co-located.
- Observed non-simultaneous peak consumption is 3282 MW; simultaneous peak consumption is 2815 MW.
- Discussion on whether the load is flexible or not: currently no such categorization in the process, dependent on future commission projects.
- By 2028, ERCOT has effectively approved a little over 14 gigawatts for large loads.
- Clarification on load ramps and submission requests: both the load ramp and potential transmission upgrades are considered.
3 – NPRR1238 Discussion – ERCOT Staff
- Discussion on NPRR1238, focused on how the language might adjust load shed percentages.
- Clarification on concerns and misunderstandings about NPRR1238 raised by stakeholders, especially regarding its impact on NOIE areas.
- Explanation of the intent behind NPRR1238: to remove interruptible loads from load shed tables and calculate requirements based on actual firm loads.
- ERCOT’s ongoing efforts to develop scenarios based on NPRR1238 language and its load shed impacts.
- Stakeholder concerns about sequencing NPRR1238 with NPRR1234 due to dependencies and the need to move forward collectively.
- Discussion on using NPRR1238 during transmission emergencies and its limitations, with suggested clarifications in the language.
- Importance of moving NPRR1238 along with NPRR1234 due to interconnect limitations and urgency emphasized by stakeholders.
- ERCOT working to provide comments about timeline with NPRR 1234 and to bring a scenario for discussion to the OWG surrounding load shed percentages
- Methodologies for calculating load shed percentages explained, including considerations of changing load ratios over time.
- Approval of NPRR expected around Q1 of next year.
- Manual nature of load shed processes and preference for system-based operations over manual management highlighted.
- Stakeholders’ input sought on the desired length of time for exiting the VECL program and related operational considerations.
- Acknowledgment that changes in load dynamics and flexible loads over time will necessitate ongoing adjustments.
- Consensus on creating a path for transitioning between different load categories, with considerations for transmission studies, interconnection agreements, and system updates.
- Estimated minimum six-month timeline for implementing major changes in load registrations and categories stressed for reliability reasons.
4 – Maximum Size of Single Large Load Connection – Discussion of Revised Concept – ERCOT Staff
Key Topics Discussed:
- Feedback from previous meeting and internal discussions led to a revised approach to large load connections.
- Concept to simplify large load interconnection with a focus on a 1000 MW limit at a single point.
- Plans to file a PGRR (Protocol Revision Requests) and update planning criteria.
- Potential need for updated studies to validate the 1000 MW limit, based on Southern Cross project.
- Operation challenges in maintaining grid stability with large load connections.
Major Decisions Made:
- In comments to PGRR115, a new paragraph will limit large load interconnection at a single point to 1000 MW.
- A separate PGRR will establish that no more than 1000 MW can be lost for any single contingency in a planning study.
- ERCOT will commit to updating studies before final approval of these changes to ensure reliability.
Questions and Concerns Raised:
- Clarification on the term ‘single point of interconnect’ there are ongoing discussions on using either POI or POIB.whether POI or another definition.
- Management of faults in ring bus or breaker schemes; distinction between voltage ride-through and contingency scenarios.
- Modeling requirements for stability studies and potential updates for better load model accuracy.
- Possibility of grandfathering existing points of interconnection versus requiring compliance with new criteria.
- Operational feasibility and potential design challenges if loads exceed the 1000 MW threshold, particularly concerning process interconnections.
Follow-up Actions Planned:
- ERCOT to work on drafting and filing comments for PGRR115 and a separate PGRR for a new planning criterion.
- ERCOT to conduct updated studies to validate or adjust the 1000 MW limit based on current data and scenarios.
- Further discussions and engagement anticipated with stakeholders to refine and finalize these plans.
5 – Schedule of Future Meetings – Bill Blevins/Bob Wittmeyer
- Participant: Bill Blevins
- Discussion:
- The task force hasn’t met initial expectations such as developing ways for flexible loads to participate in ancillary services.
- After completing NPRR134, PGRR115, and NPRR1238, it may be time to hibernate the task force.
- Future issues to be presented by the legislature by next June are anticipated.
- Discussion:
- Participant: Martha Henson
- Discussion:
- Clarification requested on the handling of ERCOT NPRR1234.
- Anticipated that future comments on NPRR1234 will be discussed at ROS.
- Discussion:
- Participant: (unknown)
- Discussion:
- Suggests hibernating after the current meeting unless specific issues arise, like interconnection discussions.
- Discussion:
- Participant: Clayton Stice
- Discussion:
- Discussion on managing transition between CLR and non CLR within markets area.
- Recommendation to shift this discussion to relevant markets forums like WMS or WMWG.
- Discussion:
- Participants: Group Discussion (General)
- Discussion:
- Question on nodal versus non-nodal status raised, with emphasis on consistent nodal load.
- Some loads seek to switch based on market conditions, suggesting consistent nodal status to prevent such shifts.
- Attempts to expand nodal pricing to all large loads were discussed but lacked support.
- Discussion:
- Participant: Lee Bracher
- Discussion:
- Bitcoin mining and large load participation awareness in other forums suggested.
- Broadly supportive for nodal pricing.
- Brought up the need to address interconnection queue and PFR requirements for CLRs.
- Discussion:
- Participants: Agee Springer
- Discussion:
- Clarified that issues needing NPRR1188 is separate from PFR requirements for CLRs.
- Discussed timelines for NPRR1188 and related actions.
- Discussion:
- Participant: Michael Jewell (Priority Power)
- Discussion:
- Provided updates on timelines for NPRR1244 related to NOGRR263, at PRS next week.
- Discussion:
- Discussion:
- Queue updates to continue at WMS unless a more public reporting method is established.
- Participants: Group Discussion on Next Steps
- Discussion:
- Cancellation of some scheduled LFL meetings anticipated unless specific issues arise.
- Request to TAC for guidance on the best venue for queue updates.
- Discussion:
Meeting Adjourned.
NPRR1238 – NPRR1234 – PGRR115
Keyword Tags: OWG | PGRR | POI | ERCOT