Meeting Summary - 09/11/24 WMS Meeting

Meeting Summary - 09/11/24 WMS Meeting

0 – Validation for WMS Standing Representatives – Pamela Hanson

1 – Antitrust Admonition – Eric Blakey

2 – Agenda Review – Eric Blakey

3 – Approval of WMS Meeting Minutes – Vote – Eric Blakey

  • July minutes will be added to the combo ballot for approval.

4 – Technical Advisory Committee TAC Update – Eric Blakey

  • Stakeholder process was the major topic of discussion.
  • Chairman Gleason commented on improvements needed for the stakeholder process.
  • TAC workshop scheduled for the fifth was canceled and will now be the first topic at the next TAC meeting on September 19.
  • The TAC meeting on September 19 will start at 09:00 am and the first two hours will be focused on the stakeholder process.
  • Further discussion on the stakeholder process will occur under agenda item 15.
  • WMS report was presented and generally well received, though there were comments.
  • TAC chair Caitlin Smith appreciated the collaboration with the IMM and his presentation on the state of the market report.
  • There will be further discussion on TAC assignments and open action items under item 15.

5 – ERCOT Operations and Market Items

5.1 – Proposed Changes to Ancillary Service Methodology for 2025 – Vote – Luis Hinojosa

  • Presented a high-level overview and proposed changes to the 2025 Ancillary Service (AS) Methodology.
  • Initial discussions kicked off in July and continued with ROS and TAC.
  • Changes in regulation service from net load ramping to forecasted net load error.
  • Adjustments to generation to be dispatched (GTBD) application to use net load forecast error.
  • Three changes in ERCOT: 
    • Removal of 90th percentile minimum for sunset hours,
    • Adjusted the frequency recovery portion of accounting for historical load to the 70th percentile, matching RRS methodology.
    • Compute the minimum ECRS requirements as the larger of the capacity needed to recover frequency and capacity needed to support net load forecast errors.
  • Non-spin service changes: using 4-hour net load forecast error for low peak hours and 6-hour ahead methodology for others.
  • No changes in RRS methodology, but changes to the IFRO resulting in new minimum RSPFR limit for 2025 at 1,365 MW from 1,185 MW.
  • Proposed methodology sheets and quantities by month will be updated and presented to TAC next week.
  • Questions raised about potential regulation shortfalls in winter mornings and their risks.
  • Discussion on possible nesting methodology for non-spin and ECRS proposed by IMM.
  • General support for ERCOT’s proposed plans but suggestions for PUC involvement in policy settings.

Decisions:

  • To endorse proposed changes to the Ancillary Service Methdology for 2025 as submitted by ERCOT Staff.

5.2 – Congestion Revenue Rights Auction Mitigation – Samantha Findley

  • Performance issues in long-term auctions, especially those spanning three years.
  • Increase in settlement points, registered CRRAH account holders, and counterparties causing constraints on optimization.
  • Historical performance issues: A recent sequence took 363 hours to converge on a solution, causing delays.
  • Medium and long-term market design changes proposed to improve auction performance.
  • Short-term mitigation includes new per TOU limits, potentially setting a transaction adjustment period to ensure timely auction solutions.
  • Potential changes discussed: Lowering per account holder limits, increasing minimum bid prices, removing multi-month bid functionality, and modifying capacity percentages for long term auctions.
  • Concerns about the future impact due to increasing CRRAH account holders and settlement points.
  • Sympathy expressed for stakeholders facing disruption in congestion hedging strategies with limited notice.
  • Discussion on hardware and software optimizations undertaken, including running up to 28 CPUs.
  • Feedback from stakeholders on improving systems, concerns over potential limits, and future planning for system capacity.

5.3 – Large Load Interconnection Report – Manuel Navarro Catalan – Chris Cosway

  • Significant growth in co-located and standalone projects.
  • Standalone projects make up the majority of new megawatts and are growing faster.
  • Current total queue capacity increased by 4,439 MW since last month.
  • Significant increase in projects with in-service dates in 2028.
  • Most megawatts are under ERCOT review due to pending and under review studies.
  • Slight decrease in planning studies approved recently, but steady approved energized megawatts.
  • 5,496 MW approved to energize, with a notable amount in the west load zone and consisting mostly of standalone projects.
  • Observed a steady increase in non-simultaneous peak load and simultaneous peak consumption.

Bill Barnes

  • Request to provide information on what has actually been energized.
  • Include a breakdown of loads by type if possible.
  • Request for a timeline on the remaining approved loads.

Brian Sams

  • Echoed Bill Barnes’ comments on the need for more transparency.
  • Emphasis on the importance of understanding potential double counting in the large load queue.
  • More transparency would add credibility to long-term load forecasts.

Seth Cochran

  • Inquired about the expected timeline for projects to come online.
  • Questioned the proportion of projects that might not come online.
  • Asked about the duration for which projects can stay in the queue without progress.

Bob Wittmeyer

  • Noted the necessity of considering load ramp schedules.
  • Suggested a legal review of sharing limitations.
  • Commented on the hibernation of the large flexible load task force.
  • Referred to NPRR1202 dealing with queue filtering and associated fees.

Ian Haley

  • Supported the idea of including connected loads in reports for clarity.

General Discussion

  • Overall transparency and detailed breakdowns in reports are crucial for stakeholders.
  • Continuation of monthly reports to address evolving questions from stakeholders.

6 – Wholesale Market Working Group – WMWG – Amanda Frazier

6.1 – NPRR1235 Dispatchable Reliability Reserve Service Discussion

  • ERCOT outlined their comments from August 23.
  • High-level discussion about adding ESRs to the service with no real consensus or plan to endorse.
  • Understanding that ESRs wouldn’t be added in phase one.
  • ERCOT committed to continue looking at the issue and to file an NPRR this year but did not commit to moving forward with phase two.
  • Details of comments from the NPRR were reviewed to highlight specific policy decisions embedded in the language.
  • Reminder for market participants to review the detailed NPRR.

6.2 – NPRR1229, CMP Payment Policy Questions Discussion

  • This was the second discussion on NPRR1229, which was filed by STEC following an incident with one of their plants.
  • The proposal involves a payment for when ERCOT implements a CMP if it impacts a generator.
  • ERCOT has policy concerns about this NPRR and has engaged with STEC and market participants offline.
  • There is a consideration whether this issue should be elevated to TAC for higher-level policy discussions.
  • A clarification was made that there was no specific incident of a unit trip offline, but it’s more about what actions are needed if such an event occurs.
  • Decision on WMS’s recommendation is postponed until item twelve, 

6.3 – NPRR1238, Voluntary Registration of Loads with Curtailable Load Capabilities – ORDC Implications

  • Luminant proposed a change but decided not to pursue it due to timing with real-time co-optimization.
  • The issue is considered OBE (overtaken by events) and will not stay on the discussion for WMW.

6.4 – NPRR1241 Firm Fuel Supply & Hourly Standby Fee

  • Discussion on changes to the calculation of the hourly standby fee for firm fuel service.
  • ERCOT reviewed the NPRR and is open to discussions about it, but no substantive agreement was reached.
  • Initial discussion, NPRR1241 had not been reviewed by PRS or WMS yet.
  • Consideration of tabling the NPRR and referring it back to WMWG for further discussion was proposed.
  • ERCOT is internally reviewing the NPRR and might provide suggestions for improvement.

6.5 – NPRR 1230 / Other

  • NPRR1230 will be monitored by CMWG instead of WMWG moving forward.
  • Awaiting further internal suggestions from ERCOT.
  • Potential tabling and referral of NPRR1241 to WMWG.

7 – Demand Side Working Group – DSWG – Nathaniel Mancha

  • Skipped to second slide to save time, focusing on the 4CP update.
  • ERCOT provided an update on ADER and some NPRRs.
  • Presented two alternatives for a 4CP adjustment solution
    • Increasing market transparency with daily reports or telemetry data.
    • Removing WSL from 4CP calculations.
  • Concern over the growing impact of WSL adjustments on load data and pricing.
  • Proposal to remove WSL from certain calculations for quicker demand side insights.
  • Discussion on implementing these recommendations and the responsible parties for NPRRs.
  • Mark provided an update: difficulty in implementing changes due to PUC rule implications on WSL calculations.
  • A market participant filed an SCR to request WSL through ICCP; ERCOT recommended converting it into an NPRR. Draft NPRR has been submitted.
  • Current telemetry does not allow for direct calculation of WSL in real-time. The energy storage resource dashboard is used as a proxy.
  • Agreement on the importance of real-time data over daily extracts.
  • Discussion on ERCOT’s role in sponsoring NPRR filings.

8 – Demand Side Working Group – DSWG – Nathaniel Mancha

  • Topic: VCMRR042 – Verifiable Cost Manual Revision Request
    • Related to SO2 and NOx emission prices
    • Seasonal index pricing: May to September
    • Annual index pricing: October to April
    • New concept for ERCOT’s monthly calculation process: average for first 15 days of prior month
    • Seasonal pricing starts at approximately $850 per short ton
    • Monthly adjustments paused with a plus/minus 10% threshold
  • Topic: Grey Box Language Addition
    • Addressed process changes for future automation
    • Need for clarity on manual vs. automated processes
    • Vistra and ERCOT to meet offline for further discussion
  • Topic: New Concept for Emission Cost Recovery
    • Concerns about QSA running out of emission credits
    • Purchases of additional credits not covered under current verifiable cost manual
    • Dispute-based recovery model proposed
    • Eligible recovery to be uplifted to load on an LRS basis
    • Group seeks to disincentivize over-procurement and credit only actual consumption
    • Language modification and clarity requested
    • There will be further discussion surrounding alternative options.
  • Topic: Future Meeting Plans
    • October meeting date pending
    • Progress on earlier discussed topics to determine date

9 – Supply Analysis Working Group – SAWG – Kevin Hanson

  • Pete Warren presented on the CONE / Peaker net margin threshold draft NPRR.
  • ERCOT will revisit the CONE Peaker topic after the 8/29 PUC open meeting.
  • PUC adopted $140 kw per year as a cone for studies based on a frame CT reference technology.
  • PUC adopted $140 kw per year as the CONE for planning studies based on a frame CT reference technology.

10 – WMS Revision Requests Tabled at WMS – Possible Vote – Eric Blakey

  • Both requests can remain tabled.

10.1 – SMOGRR028, Add Series Reactor Compensation Factors – MWG

  • Reached out for an update; ERCOT is still working on technical comments.
  • The technical routine is the reason for the delay.
  • Plan to keep this matter tabled to MWG.

10.2 – VCMRR042, SO2 and NOx Emission Index Prices Used in Verifiable Cost Calculations – RCWG

  • Language is being developed for VCMRR042.
  • Will discuss VCMRR042 further at RCWG.

11 – New Protocol Revision Subcommittee – PRS – Referrals – Vote – Eric Blakey

11.1 – NPRR1241, Firm Fuel Supply Service – FFSS – Availability and Hourly Standby Fee

  • Discussion on NPRR1241 regarding firm fuel supply service availability and hourly standby fee.
  • Request for formal referral to WMWG (Wholesale Market Working Group) was noted.
  • Need for further refinement of clawback and/or withholding amounts based on past seasons’ berm fuel deployment experiences.
  • Changing proportionality criteria for maximum clawback on unavailability.
  • NPRR aims to align performance incentives with respective risks.
  • Request to continue discussions with ERCOT and WMWG.
  • Suggestion to table and refer the matter to WMWG for further discussion.
  • No opposition or concerns raised regarding the referral.

12 – Revision Requests Tabled at PRS and Referred to WMS – Possible Vote – Eric Blakey

12.1 – NPRR1070, Planning Criteria for GTC Exit Solutions

  • No new updates on NPRR1070.

12.2 – NPRR1200, Utilization of Calculated Values for Non-WSL for ESRs – MWG

  • NPRR1200 MWG is not met.

12.3 – NPRR1202, Refundable Deposits for Large Load Interconnection Studies – WMWG

  • The item is currently hibernated.
  • WMSWG has completed all necessary actions they are aware of.
  • Suggestion to keep the item tabled at WMS.
  • Awaiting comments from different parties.
  • No vote required.

12.4 – NPRR1214, Reliability Deployment Price Adder Fix to Provide Locational Price Signals, Reduce Uplift and Risk – CMWG

  • NPRR1214 is still under review by CMWG.

12.5 – NPRR1229, Real-Time Constraint Management Plan Energy Payment – WMWG

  • Discussion about NPRR1229 potentially being addressed as a policy decision at the PUC due to the policy questions it has raised.
  • Suggestion to deny the request and allow an appeal to the commission as a more formal process.
  • Clarification needed on the process TAC would use to handle the policy questions.
  • A question was raised if there had been any briefings from STEC to the commission on this issue.
  • Lucas Turner responded there has been no outreach on policy questions but is working on comments to address some questions.
  • There is ongoing communication with STEC for language clarification on NPRR1229.
  • ERCOT has posted policy questions for WMWG but has not received responses.
  • Discussion on the need to address policy questions meaningfully to clarify NPRR1229.
  • Mention of significant policy questions like compensation to generators when they trip offline and opportunity costs.
  • Consensus that policy questions require more detailed answers before ERCOT can clarify NPRR1229.
  • Suggestions for the WMS’ next steps, including possibly moving the discussion forward at the WMWG.

12.6 – NPRR1235, Dispatchable Reliability Reserve Service as a Stand-Alone Ancillary Service – SAWG and WMWG

  • Katie Riche discussed NPRR1235 about Dispatchable Reliability Reserve Service as a standalone ancillary service.
  • ERCOT plans to bring additional language for storage participation in DRRS.
  • ERCOT will ask PRS for direction on phase two.
  • Katie Rich requested that NPRR1235 be brought back next month for further discussion.
  • Dan Mantina from ERCOT presented an update on summer drought risk.
  • Pete Warkin discussed reliability standard updates and a presentation filed at the PUC.
  • Pete Warkin also discussed the CONE/VOLL studies; ERCOT filed the Brattle volume study on August 22.
  • The PUC adopted a $35,000 price for planning study volumes, increased from the initially proposed $30,000.
  • Discussions on December 2024 CDR planning process led by Pete Warkin.
  • ERCOT board approved NPRR1219, with PUC approval expected in September, and supplemental tabs to be added from May 2025.
  • Upcoming ELCC stay for storage between early to mid-October and a new NPRR for thermal resources by ERCOT.
  • Change in providers for developing solar wind shapes, with an announcement expected upon identification of the new company.
  • Next meeting in October; September 27 meeting canceled.
  • David Dalitsch asked for clarification on NPRR1235 discussion needs at SAWG.
  • Katie Rich explained NPRR1235 was tabled to discuss how it fits into resource adequacy, pending decisions from the last open meeting.

12.7 – NPRR1238, Voluntary Registration of Loads with Curtailable Load Capabilities – WMWG

  • NPRR1238 was discussed previously, needs approval from WMS.
  • Importance expressed to move forward urgently despite removal of urgency status.
  • Effort to align NPRR1238 with NPRR1234 mentioned.
  • Current discussions ongoing at OWG, awaiting ROS input.
  • ORDC discussion at WMWG completed, now it’s back to WMS for approval.
  • No additional language being added, related concerns addressed by ERCOT staff.
  • Oncor’s comments included issues like including interconnecting TDSPs and changing from ‘ceasing’ to ‘reducing’ consumption during curtailment.
  • Some OWG team members still reviewing the language but no opposition to advancing from WMS perspective.
  • Possibility of ERCOT creating comments to be discussed in the LFLTF
  • No objections from LFLTF regarding NPRR1238.
  • Nabaraj Pokharel queried ERCOT’s position; decision pending input from appropriate ERCOT representatives.
  • Agreement to table the item until further information is available from ERCOT.

13 – Major Transmission Elements – MTE – list – Vote – Rickey Floyd

  • Reviewed updates to MTE list from the last OWG meeting on October 15.
  • TOs presented their recommendations for removals and edits.
  • OWG reached consensus on proposed removals and edits.
  • No additions to the MTE list were recommended this year.
  • OWG recommends WMS endorses the updated list.

14 – Combo Ballot – Vote – Eric Blakey

15 – Other Business – Eric Blakey

15.1 – Review Open Action Items – Jim Lee

  • Jim Lee indicated he did not have any updates.

15.2 – Review of Stakeholder Process

  • WMS subcommittee provided an opportunity to communicate potential improvements to TAC.
  • Discussion on improving information provided to the board and commissioners.
  • Focus on significant topics like ancillary services for 2024, document 245 and 1190.
  • Consideration of changing voting requirement to two-thirds instead of 50% for better process, though the impact is uncertain.
  • Issue of transparency and governance was raised.
  • Suggestions for increasing communication visibility at the TAC level.
  • No major changes proposed at subcommittee level until further discussion at TAC.
  • Next TAC meeting announcement and reminder about the start time.
  • Open invitation for suggestions to improve WMS efficiency and communication.

15.3 – TAC assignments – Eric Blakey

  • Discussion about reviewing TAC assignments per Caitlin’s suggestion.
  • Noted the importance of working groups to review assignments related to EPA and 1230.
  • Concerns about not discussing the EPA updates in WMS and the appropriateness of current assignments.
  • Mention of old open action items and parking lot items that need review and potential removal.
  • Request for recommendations to clean out the parking lot and decide on the necessity of these items.
  • Uncertainty about the purpose of the parking lot items as they are rarely used in other subcommittees.

16 – Adjourn – Eric Blakey

    • Eric Blakey concluded the meeting.

09/11/24 – ERCOT – WMS Meeting

Related Control Numbers: NPRR1214 – VCMRR042 – NPRR1241 – NPRR1229 – SMOGRR028 – NPRR1070 – NPRR1235 – NPRR1200 – NPRR1238 – NPRR1202 – NPRR1234

Keyword Tags: ERCOT